| Line 1280: | Line 1280: | ||
| This sprint the team worked on finalizing the Wiki. Chapters that weren’t yet completed were written and some drawings were added. Also, the compost testing was finished, the first version of the final video was made and the application was improved. | This sprint the team worked on finalizing the Wiki. Chapters that weren’t yet completed were written and some drawings were added. Also, the compost testing was finished, the first version of the final video was made and the application was improved. | ||
| + | < | ||
| + | <table tlabelSprint12> | ||
| + | < | ||
| + | <WRAP center> | ||
| | sprint 12 | planned duration (h) | real duration (h) | involved members | status | | | sprint 12 | planned duration (h) | real duration (h) | involved members | status | | ||
| | Detailed drawings wiki | 1 | 2 | C | Done | | | Detailed drawings wiki | 1 | 2 | C | Done | | ||
| Line 1299: | Line 1303: | ||
| | First version Video | 16 | 11 | Q | Done | | | First version Video | 16 | 11 | Q | Done | | ||
| + | </ | ||
| + | </ | ||
| + | </ | ||
| The burndown chart shows that all work was finnished in time. Only most tasks were finished on the final day of the sprint. | The burndown chart shows that all work was finnished in time. Only most tasks were finished on the final day of the sprint. | ||
| Line 1313: | Line 1320: | ||
| </ | </ | ||
| - | |||
| ===3.11.13 Sprint 13 12/06/2025 – 18/ | ===3.11.13 Sprint 13 12/06/2025 – 18/ | ||
| + | During the last sprint all detail small details of the wiki were finished, the final presentation was prepared and the project was finished. | ||
| + | < | ||
| + | <table tlabelSprint13> | ||
| + | < | ||
| + | <WRAP center> | ||
| + | |||
| + | ^ Tasks Sprint 13 ^ Planned Duration (h) ^ Real Duration (h) ^ Involved Members ^ Status ^ | ||
| + | | WIKI 7.5 Test &c Results + 7.6 Summary | 2 | 2 | L | Done| | ||
| + | | Testing mixing and cutting with Orbeez | 1 | 0.75 | E | Done| | ||
| + | | Uploading functional testing document | 0.5 | 0.5 | L | Done| | ||
| + | | Improving video | 2 | 2 | Q | Done| | ||
| + | | WIKI 7.4.3 Software | 2 | 2 | N | Done| | ||
| + | | Include Electronics to prototype | 3 | 4 | S | Done| | ||
| + | | Logbook: Report, Minute | 0.2 | 0.2 | Q | Done| | ||
| + | | Upload Code to Deliverables | 0.2 | 0.2 | N | Done| | ||
| + | | Lay out + upload Final Report | 2 | 2 | S | Done| | ||
| + | | Lay out Final Presentation + upload | 2 | 2 | C | Done| | ||
| + | | Home Page WIKI: Brief Goals & Requirements | 0.75 | 0.75 | E | Done| | ||
| + | | WIKI Report Acknowledgements & Abstract | 1 | 1 | Q | Done| | ||
| + | | WIKI: Update project management sprint 12 & 13 | 3 | 3 | E | Done| | ||
| + | | 7.5.4 Test & Results - Mechanical | 1 | 1 | E | Done| | ||
| + | | 7.6 Summary | 0.75 | 0.75 | L | Done| | ||
| + | | Slides: Problem + UN Sustainability | 0.5 | 0.5 | L | Done| | ||
| + | | Slides: Requirements & Concept | 2 | 2 | E | Done| | ||
| + | | Slides: Solution (product + app) | 2 | 2 | C | Done| | ||
| + | | Slides: Prototype | 1 | 1 | S | Done| | ||
| + | | Slides: Functional results - mechanical | 1 | 1 | S | Done| | ||
| + | | Slides: Conclusion + future development | 2 | 2 | Q | Done| | ||
| + | | Slides: Functional results - electronics | 1 | 1 | N | Done| | ||
| + | | Final slide: Flyer + leaflet | 1 | 1 | C | Done| | ||
| + | | 7.4.4 Test & Results - Compost | 0.5 | 0.5 | L | Done| | ||
| + | |||
| + | |||
| + | </ | ||
| + | </ | ||
| + | </ | ||
| + | |||
| + | The final burndown chart shows a good workflow as the curve is going down very steady during the week. | ||
| + | |||
| + | {{:: | ||
| + | <figure flabelBurndownChartS12> | ||
| + | |||
| + | < | ||
| + | |||
| + | </ | ||
| + | |||
| + | |||
| Line 1354: | Line 1407: | ||
| | 12 |finished all tasks| Changing estimated times in Jira| |change estimated times in Jira | | | | 12 |finished all tasks| Changing estimated times in Jira| |change estimated times in Jira | | | ||
| | |working in library together | | | | | | | |working in library together | | | | | | ||
| + | | 13 |finished all tasks| | | | | | ||
| + | | |Final presentation went well| | | | | | ||
| + | | |positive feedback after the final presentation | | | | | | ||
| </ | </ | ||
| </ | </ | ||
| Line 2341: | Line 2396: | ||
| === - Software === | === - Software === | ||
| - | Describe in detail | + | The figure {{ref> |
| - | (// | + | Once he is logged, the user access |
| - | (//ii//) selection of development platforms and software components (use tables | + | Finally, it's possible to go back to log in page via the disconnect button. \\ |
| - | (//iii//) component diagram. | + | {{: |
| + | |||
| + | < | ||
| + | <figure flabelUse_case> | ||
| + | < | ||
| + | </figure> | ||
| + | </WRAP> | ||
| === - Packaging === | === - Packaging === | ||
| Line 2833: | Line 2894: | ||
| ==== - Summary ==== | ==== - Summary ==== | ||
| - | //Provide here the conclusions | + | |
| + | This chapter described | ||
| + | |||
| + | The second section covers the ideation phase and the creation of initial sketches. Important considerations during | ||
| + | |||
| + | The third part explains | ||
| + | |||
| + | The fourth section provides a more detailed analysis of the design. Using theoretical knowledge and the initial sketches, functional and detailed drawings of the Loopbin were created. These illustrated the structure of the product and the way it worked. The choice of materials was based on a comparison of several options to determine the most suitable choice. In addition, a 3D model of the product was developed and subjected to a stress analysis, which the product successfully passed. In addition to the mechanical aspects, the hardware and software components were also developed. Furthermore, | ||
| + | |||
| + | The fifth part describes the development of the prototype and the app that is coming with the product. Both were tested and evaluated, as well as the testing of the composting process itself. All tests delivered positive results. | ||
| + | |||
| + | Each of these steps, from development to final product and prototype, played a crucial role in this project and was successfully completed. The next chapter | ||
| + | |||
| ===== - Conclusions ===== | ===== - Conclusions ===== | ||
| Line 2846: | Line 2920: | ||
| ==== - Future Development ==== | ==== - Future Development ==== | ||
| - | Future improvements could focus on making the product easier and more comfortable to handle by enhancing | + | Future improvements could focus on making the product easier and more comfortable to handle by enhancing |
| + | |||
| + | The product design could be refined, with continuous updates to materials using state-of-the-art options. Adding transparent elements would allow users to view the composting process inside. Making the handles retractable could also reduce the risk of tripping or injury near the device. | ||
| + | |||
| + | Improving the installation of electronic components could make the product easier to assemble and maintain. Strengthening the app’s cybersecurity features, such as enhanced data protection would help prevent information leaks. Additionally, | ||
| - | Adding transparent materials | + | Lastly, new markets and target audiences could be expanded |
| - | Improving how electronic components are installed could make the product easier to assemble and maintain. It is also important to strengthen the app’s cybersecurity features, including better data protection to prevent information leaks. Additionally, | ||