| report [2025/06/15 15:13] – [7.4 Design] team3 | report [2025/06/23 15:17] (current) – [3.12 Sprint Evaluations] team3 | ||
|---|---|---|---|
| Line 1280: | Line 1280: | ||
| This sprint the team worked on finalizing the Wiki. Chapters that weren’t yet completed were written and some drawings were added. Also, the compost testing was finished, the first version of the final video was made and the application was improved. | This sprint the team worked on finalizing the Wiki. Chapters that weren’t yet completed were written and some drawings were added. Also, the compost testing was finished, the first version of the final video was made and the application was improved. | ||
| + | < | ||
| + | <table tlabelSprint12> | ||
| + | < | ||
| + | <WRAP center> | ||
| | sprint 12 | planned duration (h) | real duration (h) | involved members | status | | | sprint 12 | planned duration (h) | real duration (h) | involved members | status | | ||
| | Detailed drawings wiki | 1 | 2 | C | Done | | | Detailed drawings wiki | 1 | 2 | C | Done | | ||
| Line 1299: | Line 1303: | ||
| | First version Video | 16 | 11 | Q | Done | | | First version Video | 16 | 11 | Q | Done | | ||
| + | </ | ||
| + | </ | ||
| + | </ | ||
| The burndown chart shows that all work was finnished in time. Only most tasks were finished on the final day of the sprint. | The burndown chart shows that all work was finnished in time. Only most tasks were finished on the final day of the sprint. | ||
| Line 1313: | Line 1320: | ||
| </ | </ | ||
| - | |||
| ===3.11.13 Sprint 13 12/06/2025 – 18/ | ===3.11.13 Sprint 13 12/06/2025 – 18/ | ||
| + | During the last sprint all detail small details of the wiki were finished, the final presentation was prepared and the project was finished. | ||
| + | < | ||
| + | <table tlabelSprint13> | ||
| + | < | ||
| + | <WRAP center> | ||
| + | |||
| + | ^ Tasks Sprint 13 ^ Planned Duration (h) ^ Real Duration (h) ^ Involved Members ^ Status ^ | ||
| + | | WIKI 7.5 Test &c Results + 7.6 Summary | 2 | 2 | L | Done| | ||
| + | | Testing mixing and cutting with Orbeez | 1 | 0.75 | E | Done| | ||
| + | | Uploading functional testing document | 0.5 | 0.5 | L | Done| | ||
| + | | Improving video | 2 | 2 | Q | Done| | ||
| + | | WIKI 7.4.3 Software | 2 | 2 | N | Done| | ||
| + | | Include Electronics to prototype | 3 | 4 | S | Done| | ||
| + | | Logbook: Report, Minute | 0.2 | 0.2 | Q | Done| | ||
| + | | Upload Code to Deliverables | 0.2 | 0.2 | N | Done| | ||
| + | | Lay out + upload Final Report | 2 | 2 | S | Done| | ||
| + | | Lay out Final Presentation + upload | 2 | 2 | C | Done| | ||
| + | | Home Page WIKI: Brief Goals & Requirements | 0.75 | 0.75 | E | Done| | ||
| + | | WIKI Report Acknowledgements & Abstract | 1 | 1 | Q | Done| | ||
| + | | WIKI: Update project management sprint 12 & 13 | 3 | 3 | E | Done| | ||
| + | | 7.5.4 Test & Results - Mechanical | 1 | 1 | E | Done| | ||
| + | | 7.6 Summary | 0.75 | 0.75 | L | Done| | ||
| + | | Slides: Problem + UN Sustainability | 0.5 | 0.5 | L | Done| | ||
| + | | Slides: Requirements & Concept | 2 | 2 | E | Done| | ||
| + | | Slides: Solution (product + app) | 2 | 2 | C | Done| | ||
| + | | Slides: Prototype | 1 | 1 | S | Done| | ||
| + | | Slides: Functional results - mechanical | 1 | 1 | S | Done| | ||
| + | | Slides: Conclusion + future development | 2 | 2 | Q | Done| | ||
| + | | Slides: Functional results - electronics | 1 | 1 | N | Done| | ||
| + | | Final slide: Flyer + leaflet | 1 | 1 | C | Done| | ||
| + | | 7.4.4 Test & Results - Compost | 0.5 | 0.5 | L | Done| | ||
| + | |||
| + | |||
| + | </ | ||
| + | </ | ||
| + | </ | ||
| + | |||
| + | The final burndown chart shows a good workflow as the curve is going down very steady during the week. | ||
| + | |||
| + | {{:: | ||
| + | <figure flabelBurndownChartS12> | ||
| + | |||
| + | < | ||
| + | |||
| + | </ | ||
| + | |||
| + | |||
| Line 1354: | Line 1407: | ||
| | 12 |finished all tasks| Changing estimated times in Jira| |change estimated times in Jira | | | | 12 |finished all tasks| Changing estimated times in Jira| |change estimated times in Jira | | | ||
| | |working in library together | | | | | | | |working in library together | | | | | | ||
| + | | 13 |finished all tasks| | | | | | ||
| + | | |Final presentation went well| | | | | | ||
| + | | |positive feedback after the final presentation | | | | | | ||
| </ | </ | ||
| </ | </ | ||
| Line 2341: | Line 2396: | ||
| === - Software === | === - Software === | ||
| - | The figure {{ref> | + | The figure {{ref> |
| + | Once he is logged, | ||
| + | Finally, it's possible to go back to log in page via the disconnect button. \\ | ||
| {{: | {{: | ||